| Copy of
correspondence received from Lincolnshire County Council
dated 13th February 2006 BOSTON TRANSPORT STUDY
- PROGRESS TO DATE
The Project Brief identified that SRG3 (Stakeholder
Reference Group 3) would "take the form of a letter
which will set out progress to date, including the
results of the qualitative appraisal." Therefore the
purpose of this letter is to inform you of the next
stage of the study. As you will recall, the Study is
being carried out to see how transport problems in
Boston can be tackled up to the year 2021. The aim is to
make Boston and its surrounding area a more attractive
place in which to live, work and visit, by identifying a
Transport Strategy for future implementation in Boston.
By completion, in the summer of 2006, the study
will have: -
• Identified existing and future transport
problems in Boston, and, where possible, quantified
them
• Identified desirable outcomes that the Transport
Strategy should achieve
• Identified those options that should be assessed
• Assessed those options against the criteria and
using the methodology set out below to determine
whether they should be included in the final
Strategy
• Consulted with key Stakeholders during the course
of the Study at the SRG2 (Stakeholder Reference
Group 2) event
• Consulted with the public and key Stakeholders on
the various packages towards the end of the Study at
a venue near the centre of Boston
• Produced a vision report for the implementation of
the study outcomes
Where Are We Now?
Transport Problems
The transport problems and issues within Boston were
presented at the Stakeholder Reference Group workshop
held on 6 September 2005, and there was broad agreement
from those present that these were correct. The problems
identified and agreed are summarised below :
Problem 1 - High volumes of traffic on A16 & A52
through the town
Problem 2 - Congestion at A52 Liquorpond Street/A16
Haven Bridge Road/A16 Spalding Road junction
Problem 3 - Congestion at Al 6 Haven Bridge Road/A16
John Adams Way/Port junction
Problem 4 - Large number of small car parks spread
out around the town centre, with poor signage to
them
Problem 5 - Rat-running traffic using inappropriate
roads, both residential and rural roads
Problem 6 - Poor "Town" bus service
Problem 7 - Unreliable bus services due to
congestion
Problem 8 - Bus services in peak hours are primarily
for educational users, not commuters
Problem 9 - Buses and bus station lack modern
facilities
Problem 10 - Cycle/vehicle conflicts, leading to
accidents
Problem 11 - Pedestrian/vehicle conflicts, leading
to accidents, delays and severance
Problem 12 - Localised poor air quality (Air Quality
Management Area)
Problem 13 - Future development sites situated away
from existing housing and transport facilities
Strategy Outcomes
"Strategy Outcomes" are the specific results that the
Transport Strategy should achieve on the ground in
Boston. Since the last Stakeholder Reference Group
event, the Outcomes have been discussed and agreed by
the Study Team (the Joint Officer Group). The agreed
Outcomes are summarised as follows:
Outcome A - To have less traffic on inappropriate
routes
Outcome B - A reduction in the number and severity
of crashes (all modes)
Outcome C - Reduced delays for traffic on A52/Al 6
corridor with safe facilities for vulnerable users
Outcome D - Improved access to facilities,
especially for those who are mobility impaired and
those without access to a car
Outcome E - Improved road safety for Non Motorised
Users, especially in the vicinity of schools
Outcome F - Improved cycling and pedestrian
management in the town centre
Outcome G - Greater clarity and consistency of
priority within the highway for all users
Outcome H - Improved connectivity between shopping
areas and public transport facilities
Outcome I - Priority for Public Transport into and
within the town centre
Outcome J - Increased public transport access and
provision
Outcome K - Improved air quality in the Air Quality
Management Area (AQMA)
Outcome L - Reduced car usage for trips wholly
within Boston
Outcome M - Effective management of car parking
Outcome N - Limiting the impact of development
Outcome O - Improved cross-town movements
Options Accepted, Rejected and "Ongoing"
At the SRG2 event, various options were presented by
the study team for consideration for possible inclusion
in the final Transport Strategy. SRG members also
suggested additional options. All the Options that met
the strategy outcomes and were both viable and cost
effective were then taken forward into a "sifting"
process, known as Qualitative Appraisal, to see if any
of the Options could be rejected at an early stage -
this would allow the appraisal time to be concentrated
on only assessing those Options that were considered
feasible. The criteria against which they were judged
and the methodology is described below:
Criteria & Methodology
The Qualitative Appraisal of all the options listed
above was carried out by the Study Team (the Joint
Officer Group). This "sifting" process was carried out
using the following steps. Firstly, each option was
assessed to decide whether it was :
• Feasible from an engineering/planning point of
view
• Publicly and politically acceptable
• Deliverable from a cost/funding source point of
view
If the answer was "no" to any of the above, the
option was classified as "rejected". The remaining
options were then qualitatively appraised to assess
their contribution towards :
• Easing the agreed Problems stated above
• Achieving the agreed Outcomes stated above
• Achieving the Policy Objectives (presented at the
SRG2 workshop)
• Achieving the 5 Government Objectives
(environment, economy, safety, accessibility and
integration)
Some options were neither accepted nor rejected but
considered as `ongoing' i.e. would occur outside the
Transport Study.
The options accepted, rejected or considered to be
"ongoing" are shown in Table I below:
Table 1
| Option |
Recommendation |
| Option 1 -Bypass |
Accepted for further
testing |
| Option 2 -Distributor Road(s) |
Accepted for further
testing |
| Option 3 -"Pseudo" Bypass |
Accepted for further
testing |
| Option 4 - Additional River
Bridges |
Rejected on engineering /
cost grounds |
| Option 5 -Road Widening |
Accepted for further
testing |
| Option 7 -Public Transport
Improvements |
Accepted for further
testing |
| Option 8 -Minor Improvements
to Existing Main Roads |
Accepted for further
testing |
| Option 9 - Moderate
Improvements to Existing Main Roads |
Accepted for further
testing |
| Option 10 - Major
Improvements to Existing Main Roads |
Accepted for further
testing |
| Option 11 - Tidal Flow |
Rejected |
| Option 12 - Park & Ride Bus |
Rejected |
| Option 13- Park & Ride
(Light Rail) |
Rejected |
| Option 14 - Rail
Improvements |
Accepted for further
testing |
| Option 15 - New Bus Station |
Accepted for further
testing |
| Option 16a- Behavioural
Change Measures |
Ongoing |
| Option l6b- Demand
Management Measures |
Accepted for further
testing |
| Option 17 - Shopmobility |
Ongoing |
| Option 18 - Parking
Improvements |
Accepted for further
testing |
| Option 19 - Traffic
Management Measures |
Accepted for further
testing |
| Option 20 - Quiet Lanes |
Rejected |
| Option 21 - Water Bus |
Rejected |
| Option 22 - Extend "Non-Car"
Areas |
Accepted for further
testing |
| Option 23 - Bus Priority
Measures |
Accepted for further
testing |
| Option 24 - Buses in
Pedestrian Areas |
Accepted for further
testing |
| Option 25 - Southern Link
Road |
Accepted for further
testing |
| Option 26 -Planning
Framework to assist planning decisions |
Accepted for further
testing |
| Option 27 - Segregated
Pedestrian and Cycle Facilities on John
Adams Way |
Accepted for further
testing |
Where do we go from here?
The study has now progressed through a number of
different stages. The diagram below shows the different
stages involved, and the current percentages of
completion.

Data Collection
In order to get high quality data on the transport
situation in Boston, the following information has
been collected, checked and processed :
• Origins and Destinations of traffic, including
HGVs, travelling to, from and through Boston
• Counts of traffic for all turning movements at all
major junctions in Boston
• Counts of traffic on the major roads around Boston
using Automatic Traffic Counters
• Journey Time Surveys
• Counts of how many people board and leave buses at
the Market Place and Bus Station on a
non-market day
• Counts of how many people board and leave trains
at the Train Station on a typical day
• Review of car parking usage
• Counts of traffic using Asda and Pilgrim Hospital
Updating the Traffic Model
The Boston traffic model represents the road network
using links and nodes (nodes = junctions, links = roads
in between junctions). The previous SATURN traffic model
is now being updated to make sure that the traffic flows
and journey times are similar to real life. This is due
to be completed shortly. The model will then be
available to test relevant Strategy Packages (see
below).
What Happens Next ?
The options to be assessed further will be grouped
into "Packages". The Packages will then be tested
to allow comparisons to be made between the different
Packages. This testing is known as
Quantitative Appraisal.
A Public Consultation & SRG4 Event is planned for May
2006, to present the results of the Quantitative
Appraisal and to give the SRG members and the public the
opportunity to give their views on the various Packages.
You will be informed of the exact date and location of
this event in due course.
I hope that the above provides you with an update on
progress to date. If you have any queries or
observations on the above or have any other information
that you feel is relevant, please do not hesitate to
contact me.
Yours sincerely
(Name not published for privacy respect)
Project Manager
Boston Transport Study
|